Rednock ECO Project

Project Overview

The project is structured into 3 phases.

  1. Development

Original Project Plan

WBS
Name
Start
End
Effort
Resources
May 2022
Jun 2022
Jul 2022
Aug 2022
30
06
13
20
27
04
11
18
25
01

Start: Mon 2022-06-06 End: Fri 2022-07-29


Resources:


Precursors:


Followers:

Start: Mon 2022-06-06 End: Mon 2022-06-06


Resources:


Precursors:


Followers:

Start: Mon 2022-06-06 End: Fri 2022-07-01


Resources:


Precursors:


Followers:

Start: Mon 2022-06-06 End: Fri 2022-07-01


Resources:

Robert (Robert)


Precursors:


Followers:

Start: Tue 2022-06-14 End: Wed 2022-06-15


Resources:

Steve (Steve), Richard (Richard)


Precursors:


Followers:

Install dates (items.Calculate.WPD_PV_Install_definition) ]->[ Wed 2022-06-15

Start: Wed 2022-06-15 End: Mon 2022-06-20


Resources:

Site Team (Site)


Precursors:

Site visit (items.Calculate.WPD_Site_Visit) ]->[ Wed 2022-06-15


Followers:

Start: Mon 2022-06-06 End: Mon 2022-06-13


Resources:

Steve (Steve), Richard (Richard)


Precursors:


Followers:

Start: Mon 2022-06-06 End: Tue 2022-06-21


Resources:

David (David)


Precursors:


Followers:

Start: Mon 2022-07-04 End: Fri 2022-07-29


Resources:

Robert (Robert)


Precursors:


Followers:

1
Icon Project breakdown
ID: items
Mon 2022-06-06
Fri 2022-07-29
18.0
1.2
Icon Ecology
ID: items.Engagement
Mon 2022-06-06
Mon 2022-06-06
0.0
1.1
Icon Solar PV
ID: items.Calculate
Mon 2022-06-06
Fri 2022-07-01
7.0
1.1.3
Icon Costed options
ID: items.Calculate.Costed_PV_options
Mon 2022-06-06
Fri 2022-07-01
5.0
Robert (Robert)
1.1.2
Icon Site visit
ID: items.Calculate.WPD_Site_Visit
Tue 2022-06-14
Wed 2022-06-15
1.0
Steve (Steve), Richard (Richard)
1.1.1
Icon Install dates
ID: items.Calculate.WPD_PV_Install_definition
Wed 2022-06-15
Mon 2022-06-20
1.0
Site Team (Site)
1.3
Icon Complete_Controls_visit
ID: items.BMS_metering
Mon 2022-06-06
Mon 2022-06-13
3.0
Steve (Steve), Richard (Richard)
1.4
Icon EmonPi
ID: items.Investigate_EmonPi
Mon 2022-06-06
Tue 2022-06-21
3.0
David (David)
1.5
Icon Panoramic Power
ID: items.Investigate_Panoramic_Power
Mon 2022-07-04
Fri 2022-07-29
5.0
Robert (Robert)
All effort values are in person days.
Container Task
Normal Task
Milestone
Off-duty period

Staffing

All project phases are properly staffed. See ResourceGraph for detailed resource allocations.